Northglenn, CO Flip Project Open House Saturday Jan 31, 2009

Flip Project Open House Saturday Jan 31, 2009

Interested in following a residential flip project in real time? Welcome to our "Investor Tag Along"! Here's your opportunity to experience a flip project in person or via the web.

This Saturday Jan 31,  2 pm to 4pm we welcome you to a projection completion walk through at our Northglenn, Co flip project!  Come by between 2 and 4 pm for a tour.

It's been a busy 6 weeks but we are ready to present our Northglenn Flip project! We are down to punch list items at this point, paint touch up, smoke detectors, bath accessories, etc.

* Check out the final product prior to listing for sale

* Talk to our vendors and sub contractors

* Ask questions regarding timeline, budget, quality

 

To see project photos go to: http://activerain.com/blogsview/908324/Northglenn-CO-Flip-Project-Open-House-Saturday-Jan-31-2009

Northglenn, CO Flip Project Day #35

This weekend Jan. 17  11am to 1pm we had a good turnout for the Investor Tag Along!  Thanks to all who attended.

Started setting cabinets this weekend, uppers are in and base should be complete tomorrow.  Ordered a nice appliance package from Lowes:  Frigidaire Gas Range, 21 CF Refrigerator, Dishwasher and Microwave oven.  Saturday delivery, $1900, Lowe's likes to deal!

This week

  • Granite Tile counterops and tile back splash
  • Carpet
  • Shower doors
  • cleaning and sealing tile
  • OPEN HOUSE!   This baby is ready to hit the market!

To see project photos go to: http://activerain.com/blogsview/888249/Northglenn-CO-Flip-Project-Day-35

Northglenn, CO Flip Project Day #32

This weekend Jan. 17  11am to 1pm we'll be having our Investor Tag Along event.  All are welcome to stop by and check out the progress real time.  As all the questions about subcontractors, budgets, challenges, etc.

We are about 85% complete on our Northglenn, Co fix and Flip project. We are now officially behind schedule...probably about 1 week.   Budget is under control and quality is very good, so we'll take one for the team on schedule.

Completed:

  • Hardwood Floor refinish (awesome job, they look like new!)
  • Interior paint completed
  • Interior doors installed
  • Tile in Baths/Kitchen floor complete
  • Front porch railing installed
  • Garage interior paint complete
  • Bath Vanaties/toilets installed

Underway:

  • Assembling Kitchen cabs
  • Interior trim (base and case)
  • Painting laundry/utility room floor 

This weekend:

  • Investor Tag Along
  • Install Kitchen uppers and lowers
  • Install kitchen counter substrate and begin granite tile/backsplash

Next week:

  • Carpet
  • Shower doors
  • cleaning and sealing tile
  • OPEN HOUSE!   This baby is ready to hit the market!

To see project photos go to: http://activerain.com/blogsview/884314/Northglenn-CO-Flip-Project-Day-32

Northglenn, CO Fix and Flip Day #21
Posted:  January 05, 2009

Interested in following a residential flip project in real time?   Welcome to our "Investor Tag Along"!  Your chance to view a flip project in person or via the web.

We are about 75% complete on our Northglenn, Co fix and Flip project.  Initial schedule projected  a 4 week project, we look to be on time.   Holiday breaks are cost us a couple of days,  but overall progress and quality is good and we have encountered no major problems to date.

This weekend is interior painting, so we'll have to back off tile install until the air clears.   Hardwood floor refinishing is scheduled to start Monday, we'll allow 3 days for patching, sanding and 2 coats of polyurethane.  Carpet install to follow.

Status:

•·         All drywall texture complete

•·         6 Panel door installation 100% complete

•·         Upstairs bathroom tile complete

•·         Tile selected and on site

•·         Exterior Trim/eaves paint complete

Underway:

  • Interior paint
  • Kitchen Tile
  • Basement Bath Tile
  • Cabinets coming Saturday
  • Ordering cabinets and appliances
  • Drywall texture in basement bedrooms/living area

This week:

  • Refinish Oak hardwood floors
  • Complete Tile
  • Install Cabinets
  • Order Appliances
  • Install Basement Bath/Shower Tile
  • Install Carpet (basement)

To see project photos go to:  http://activerain.com/blogsview/862670/Northglenn-CO-Fix-and-Flip-Day-21

Northglenn, CO fix and Flip Day #15
Posted:  December 28, 2008

Interested in following a residential flip project in real time?   Welcome to our "Investor Tag Along"!  Your chance to view a flip project in person or via the web.

We are about 50% complete on our Northglenn, Co fix and Flip project.  Initial schedule projected  a 4 week project, we look to be on time.   Holiday breaks are costing the schedule a bit, but overall progress and quality is good and we have encountered no major problems to date.

Status:

  • Drywall Texture 50% complete (upstairs)
  • 6 Panel door installation 50% complete (basement)
  • Tile selected and on site

Underway:

  • Upstairs bath tile install for tub surround/floors
  • Upstairs 6 panel door and closet installs
  • Ordering cabinets and appliances
  • Drywall texture in basement bedrooms/living area

This week:

  • Complete Texture
  • Complete Interior door & closet installs
  • Order Cabinets & Appliances
  • Install Basement Bath/Shower Tile
  • Order Carpet (Basement)
  • Schedule Interior Paint

To see project photos go to:  http://activerain.com/blogsview/854659/Northglenn-CO-fix-and-Flip-Day-15

Louisville, CO-Northglenn Fix and Flip Day #10
Friday, December 26, 2008

Merry Christmas everyone!   We are taking a day off from our Northglenn, CO fix and flip.   Lot of progress these past few days:

Next Few Days: 

  • Initiate texture (orange peel) through out
  • Install 6 panel doors
  • Install 6 panel bypass sliders in closets
  • Begin Tile install in Up & Down Baths

To see project photos go to:  http://activerain.com/blogsview/851821/Louisville-CO-Northglenn-Fix-and-Flip-Day-10

 

Northglenn, Colorado Fix and Flip Investor Tag Along
Saturday, December 20, 2008

Thanks to all the folks who attended our Investor Tag Along at the Humboldt Street Flip project this past Saturday!  We had approx. 15 clients and interested parties tour the project, check out the progress.  We had our budget availalbe for review, and several folks who are evaluating their first flip project were able to review the budget and compare to the plans and progress on our project.

To see project photos go to:  http://activerain.com/blogsview/850859/Northglenn-Colorado-Fix-and-Flip-Investor-Tag-Along

 

Investor Project Walk Through Fix and Flip

Saturday, December 20, 2008

Hello Real Estate investors!  Interested in joining us on our newest flip project in Northglenn, Colorado?

Here's your chance to watch a home reconstruction from start to finish...here's what you can do:

  • Study the budgets
  • Help pick out finishes and design features
  • Learn from our mistakes
  • Make the most of it!  Maybe you'll want to try one of your own after watching this one go smoothly...

    When: Saturday December 20, 2-4 PM
    Why: Cause you've been watching to much "Flip this House" on TV, and it's time to see one up close and personal.
    Who: Rob Kelly, Realtor/Investor 
    http://www.robkellycolorado.com/

My Blog



 

Northglenn, Colorado Fix and Flip day #2

December 17th, 2008 

Day two of our fix and flip in Northglenn, Colorado. 

The home is a 2000 sq.ft, 4br/2ba/1car brick ranch with a full basement.   The home was built in 1962, has "good bones", updated dual pane vinyl windows and is in a quiet neighborhood.

Tasks completed today:

  • remove old wallpaper
  • began to patch the walls

Flip Tip: Use a wall paper scoring tool and a commercial product known as "Dif" to remove old wall paper. Most wall paper installed with a protein based adhesive.  "Dif" is an enzyme product, when applied to the scored service with warm water; the enzymes dissolve the adhesive, allowing the wallpaper to peel away easily.

To see project photos go to:  http://activerain.com/blogsview/841972/Northglenn-Colorado-Fix-and-Flip-day-2

 

Northglenn, Colorado Fix and Flip Day 1

December 16th, 2008 

Hello Investors,

Today was day one of our fix and flip in Northglenn, Colorado.  We closed last Friday on a 2000 sq.ft, 4br/2ba/1car brick ranch with a full basement.   The home was built in 1962, has "good bones", updated dual pane vinyl windows and is in a quiet neighborhood.

60 day Market Comp solds for this size home are in the $165-170k range.

This will be a resale flip, plans include: New Kitchen Cabinets and appliances, fixtures, Tile countertops and floors, refinished hardwood floors, new 6 panel doors, and exterior trim paint.